Bentley Motors
- Car Park Size: 1,378 Spaces
- PV Installation: 2.70 MWp
- PV Panels Installed: 10,652
- Annual Yield: 2,668 MWh
- Battery Storage: 6.60 MW (Estimated 2021)
- PPA Term: 30 Years
- O&M Contract: 3ti
Papilio3 at Surrey Research Park
- Installed DC power (kWp): 16.56
- System yield (kWh/kWp/year): 800
- Annual energy production (kWh): 13,116
- tCO2e saving: 65.3
- Equivalent homes powered: 82
- Equivalent road miles: 161,985
- Equivalent trees planted: 1,077
- Deployment time (hours): 24
“The 3ti solar car park is brilliant. It’s super easy to use and, unlike other EV charging systems I’ve used, it’s very reliable. I love that the Papilio3 is partly powered by renewable energy – this is the future of EV charging and should be installed in all company car parks.”
“As a first time electric car owner, using Papilio3 has been nothing but a smooth ride! Being able to drive into work, plug it in and have it charged within a couple of hours while I go on about my daily business has been a really time efficient experience, using the chargers is simple and straightforward and I've never had any troubles using the service!"
“I work at the the Surrey Technology Centre which has installed the Papilio3 EV charging hub. I have recently purchased a plug-in hybrid car, so this facility is brilliant, cutting my commuting costs and making me feel better about reducing my carbon footprint.”
"I have used the 3ti pop-up charging station at the Surrey Technology Centre for the last 5 weeks now. It has always worked smoothly, and I have always been able to find a free space. It's great to know some of the energy is coming from solar and in the hot weather it’s been a real bonus for my car to be under the shade of the panels when the rest of the car park is in direct sun. Great experience all round!"
“I’m really impressed with the Papilio3 at Surrey Technology Centre. It’s been great for me and has also made other colleagues consider an EV now that they can charge at work. I’ve always been able to get access, although at times I’ve seen it full, which is great. Hopefully we’ll see more of these around the country.”
“It has been seamless to use and never once had any issues.”
"I have been using the 3ti solar and storage charging stations since their installation earlier this year. The combination of ease of use, and the efficient use of grid/solar/storage makes it an attractive and compelling offer, providing more sustainable charging without complication to the user."
“This will help me and my family reduce our environmental impact further using this type of setup. The charge station is really easy to use and very convenient, it offers a range of charge speeds using a type 2 connection. It’s as easy as I drive to work, charge my car and when I leave at the end of the day I have a full charge through clean electricity. It really is that simple!”
"Very easy to use and a very good charging performance. A great addition to parking areas and infrastructures!"
“The option to charge my car using solar power (with a local supply back-up) means that the carbon impact of my driving is reduced even further. The Papilio3 system is conveniently located at my place of work so I don’t have to go out of my way to charge. It is also very easy to use. So overall, this provides a solution that minimises the impact on both myself and the planet.”
Previous
Next
Bentley Motors
- Car Park Size: 1,378 Spaces
- PV Installation: 2.70 MWp
- PV Panels Installed: 10,652
- Annual Yield: 2,668 MWh
- Battery Storage: 6.60 MW (Estimated 2021)
- PPA Term: 30 Years
- O&M Contract: 3ti
JP Morgan
- Car Park Size: 821 Spaces
- PV Installation: 2.24 MWp
- PV Panels Installed: 5,337
- Annual Yield: 2,352 MWh